University announces long-term development plans

Clocktower clock

Saturday 5 July 2014 3:01pm

The University of Otago Council has approved a list of building developments with an approximate value of $650 million that will further cement the University as a leading force in teaching, learning and research within New Zealand.

The list and information about the projects was presented at the Vice-Chancellor Professor Harlene Hayne’s Staff Forum today.

In a presentation to staff at the forum, the University’s Chief Operating Officer John Patrick revealed details of the projects listed on the University’s Priority Development Plan which will be evaluated for construction progressively over the next 15 years. The University Council approved the plan in principle at its last meeting in June.

The plan includes the following projects (in order of priority):

  • A new Dental School for New Zealand to replace ageing facilities. This recognises the importance of Otago’s Dental School as the only tertiary training facility for dentists in New Zealand.
  • A major renovation in the Science Precinct involving significant redevelopment of the multi-storeyed Science 1 and II buildings on the west side of the Dunedin campus. This includes the construction of new teaching and research laboratories.
  • A major upgrade of research project facilities mainly for Health Sciences in Dunedin.
  • The construction of teaching, learning and research space at the Portobello aquarium as a medium term replacement for space lost due to the closure of an earthquake-prone building at that facility.
  • A new Arts Building, replacing the older multi-storey concrete building in Albany Street. The aim is to develop a more coordinated and functional Humanities Precinct. Related to this is the replacement of the Property Services building in Albany Street to free the site for the Humanities Precinct.
  • A new Biomedical Research building, concentrating research that is currently spread throughout the Dunedin campus in the one development in the south campus area – which is south of the Museum Reserve where medical school facilities are mostly concentrated.
  • A new Marine Science teaching facility and aquarium, preferably in the harbour basin area.
  • A new Music facility, including a new Centre of Performing Arts, to be developed in the east precinct near the existing music studio in Albany Street east.
  • New facilities and additional space for the Department of Botany.
  • A new research facility in the Christchurch Health Precinct for the University of Otago Christchurch. The timing of this project is dependent on the development timeline of that precinct.
  • The redevelopment of the former Unipol building in Anzac Avenue.
  • A new student and academic services hub to be built in the area of the Union Lawn, in the heart of the Dunedin campus. The plan is to concentrate services and provide an opportunity for student-related retail development and social spaces in this important area.
  • A number of landscaping projects are detailed on the Plan. These include the landscaping of Castle Street, from Dundas Street to St David Street, the landscaping of Castle Walk on the west side of the Leith opposite the Clocktower and also Union Street from the Staff Club to University College, including renovation of the Union Street footbridge and the immediate area to the north of the Clocktower building.

A number of health and safety projects are also included on the Plan. These have a high priority and include the following.

  • Improvements to access and safety in the Commerce Building, including a new entrance directly into the atrium, removal of the existing external stairs, new internal stairs providing access from the atrium and replacement of the atrium roof
  • The completion of the refurbishment of the University of Otago, Wellington, facilities, and some further seismic strengthening
  • A continuation of the seismic strengthening work and improvements to fire safety resulting from building seismic assessments completed over the last two years

The Plan also includes reference to a number of major maintenance projects, such as refurbishment of buildings in the historic precinct, including the Clocktower.

“The intention of the Priority Development Plan is to show the University community, the public, and contractors, what we will be looking at, and focussing on, over the medium term when it comes to our built environments,” says Professor Hayne.

“We want to improve what is already a first-class experience for students, for teachers and for researchers and we want the campus to be enjoyed by the communities in which we live.

“Many of these projects were signalled in the Campus Master Plan released in 2010. This was a strategic and guiding vision of how the University should be developed in coming decades across all its three campuses and this plan follows the guiding principles in that strategic document,” she says.

Professor Hayne says the Council agreed to the priority development plan and projects within it “in principle”. However, the plan is a living document and other projects may yet be added, or removed, as situations and needs change.

Mr Patrick says the estimated cost of the projects in the plan came to $649.9 million. This figure includes projects that have already been approved or are under construction, such as the redevelopment of St David II for the Department of Applied Science, new space for Food Science in the Gregory Building and the University’s share of the costs of the enhancement of the Clocktower precinct as part of the Leith Flood Protection Scheme.

“While we do have cost estimates for each project on the Plan, we do not intend to disclose these because some projects have not been sufficiently defined and the costs are commercially sensitive.”

Mr Patrick adds that the Priority Development Plan has been prepared with the intention that it is funded without resorting to large-scale borrowing.

“Currently the University does not use debt to fund capital projects, but looking ahead, may want to do this,” Mr Patrick says.

“Funding decisions will be made as we progress planning for these projects,” he says.

Priority Development Plan

CAWSEP PROJECT NAME Rank Forecast Project Costs Planning Status Construction Related Projects
Start date Finish Date

Priority Projects Ranked

2012-06 Dental School
1
 Started   Q3 2015   Q4 2019   
2012-08 Science Precinct - Laboratory Redevelopment
2
 Started   Q3 2015   Q3 2018   
2013-16 Research Project Facilities
3
 Started   Q1 2015   Q2 2017   
  Portobello - Aquarium
4
 Q3 2014   Q2 2015   Q1 2016 
A
  Arts Replacement Building
5
 Q4 2018   Q4 2019   Q3 2022 
B
  Biomedical Sciences Research Building
6
 Q3 2014   Q2 2021   Q4 2025   
2013-02 University Teaching Facility & Aquarium Replacement
7
 TBC   TBC   TBC 
A
  Music Building  / Centre for Performing Arts
8
 Q3 2024   Q2 2025   Q1 2027   
  Botany Building
9
 Q3 2024   Q2 2025   Q1 2027   
2012-10 UOC - New Building
10
 TBC   TBC   TBC   
  Unipol Purchase and Redevelopment
11
 Q4 2024   Q3 2025   Q1 2028   
  Union Precinct Development
12
 Q4 2023   Q3 2024   Q3 2028   
 

Related Projects (Ranked with Principal Project) 

2014-04 Gregory Building - Food Science  Q4 2014   Q3 2015   Q3 2016 
C
  Property Services Building  Q1 2016   Q1 2017   Q2 2018 
B
 

Health & Safety Projects 

  Commerce Atrium  Started   TBC   TBC   
  Fire Protection  Started   Q1 2015   Q4 2028   
2013-12 UOW Refurbishment  Started   Q2 2019   Q4 2022   
  Seismic, Health and Safety  Started   Q3 2014   Q4 2028   
  Deferred Maintenance  Started   Q1 2015   Q1 2028   
2013-09 Landscaping - Union Street Bridge  Q2 2014   Q4 2014   Q2 2015   
 

Approved or Under Construction

2012-17 Department of Applied Science - St David II  Completed   Q2 2014   Q3 2015 
C
N/a Leith Flood Protection  Completed   Q4 2013   Q2 2016   
2013-08 Landscaping - Castle Street  Started   Q3 2014   Q1 2015   
 

Total Priority Development Projects

$649.9  million 

A list of Otago experts available for media comment is available elsewhere on this website.

Electronic addresses (including email accounts, instant messaging services, or telephone accounts) published on this page are for the sole purpose of contact with the individuals concerned, in their capacity as officers, employees or students of the University of Otago, or their respective organisation. Publication of any such electronic address is not to be taken as consent to receive unsolicited commercial electronic messages by the address holder.